Tuesday, October 31, 2017

How to Create Reports - Slope Stake Report

Use this dialog box to select the corridors and specify sample line groups for a cross section slope stake report. This report identifies the points of slope change for a selected corridor link.
Select Report Components
Select Corridor
Specifies the corridors to include in the report. Only corridors that are based on alignments with defined sample line groups are displayed.
Select a corridor from the list or click  to select a corridor from the drawing.
Select Alignment
Specifies the alignment to include in the report. Only the alignments contained in the selected corridor are displayed.
Select Sample Line Group
Specifies the sample line group to include in the report. Only the sample line groups for the selected alignment are displayed.
Select Corridor Link
Specifies which corridor link to use in the report. A link is defined as a single straight-line segment between endpoints on a subassembly.
Add
Adds the selected corridor, alignment, and sample line group to the List of Corridors to include in the report.
List of Corridors
Include
Lists the corridors to include in the report.
Note
When a corridor is highlighted, the start and end stations are editable. See Report Settings below.
Alignment & Sample Line Group
Lists the alignment and sample line group that you selected.
Station Start & Station End
Displays the start and end stations for the selected sample line group.
You can edit these values using the Report Settings (see below).
Delete
Removes the corridor from the list.
Report Settings
Start Station & End Station
Displays the start and end stations for a highlighted sample line group. Click a sample line group name in the list to highlight it.
You can edit these values to change the range of stations included in the report. You can enter formatted or unformatted values, such as 2+50.95 or 250.95.
Save Report To
Specifies the name and location of the resulting report.
Create Report
Generates the report and saves it to the specified location.
Done
Closes the dialog box and discards changes to station ranges.

Report Results

The slope stake report has data formatted in columns. The end columns contain information about the last two offsets in the corridor. The other columns contain information about the point codes.
End Column Descriptions
  • Row 1: Reports either cut (C) or fill (F) which is determined by the elevational difference between the last two offsets reported.
  • Row 2: Reports the distance difference between the last two offsets reported.
  • Row 3: Reports the slope value from the second-to-last offset point to the last offset point.
For example:
C 8.47
@33.87
S 1:4.00
Report Column Descriptions
  • Row 1: Reports the point code.
  • Row 2: Reports the offset value relative to 0+00.
  • Row 3: Reports the elevation value at that offset.
  • Row 4: Reports the slope from that point headed toward the next point (away from 0+00).
For example:
Daylight
-110.369
629.991
1:-4.00
Note
For slope values greater than 2:1, the value is reported as 1:X. For slope values less than 2:1, the value is reported as X%.

0 Comments:

Post a Comment

Subscribe to Post Comments [Atom]

<< Home